Christ Church Undercroft Works
|
Week Five 7th June 2004 |
||||||
|
Bricklayers have started to build the internal walls which form the new lobby and toilet. Site meetings are being held with our professional advisers to check progress. |
||||||
|
|
The new lobby between meeting room one and two takes shape. |
|
Meeting Room Two floor is now free of excess soil and is ready for cementing. |
|||
|
|
|
|
|
|||
|
|
|
Our architect Robert Chesterton of Burns Guthrie and Partners pays a visit. |
|
|||
|
|
||||||