Christ Church Undercroft Works
|
Week Three 24th May 2004 |
||||||
|
A steel "Picture Frame" roof support is installed to replace the old Choir Vestry wall. The excavator is now able to enter the undercroft and start to remove rubble and soil. |
||||||
|
|
A dumper truck moves pieces of the heavy steel "picture frame" from the delivery lorry to the undercroft. |
|
Our builders install the supports and secure them in place. |
|||
|
|
|
|
|
|||
|
The excavator moves under the church and begins to dig out and remove the soil to make a level floor for the extended meeting room. |
|
A grab lorry arrives to take away some of the rubble and soil. |
|
|||
|
|
||||||