Christ Church Undercroft Works
|
Week Fifteen 16th August 2004 |
|||||
|
The workmen cover every inch of the walls and ceilings with boarding in preparation for plastering. |
|||||
|
|
Work begins on encasing the steel columns in Meeting Room Two with plasterboard. It’s an exacting and time-consuming job. |
|
Meanwhile the boarding of Meeting Room One is almost completed. |
||
|
|
|
|
|
||
|
|
|
A lot of preparatory building work has been needed before the new exterior oak doors can be put in place. They should be coming soon. |
|
||
|
|
|||||