Christ Church Orpington

Undercroft Works 2004

Would you like to see what is going on under and around our church? You may have seen the plans, but here you can follow the action week by week as it happens.

11 May The builders Arrive. Week One

17 May Breaking Through Week Two

24 May Excavating Week Three

01 June Holes in the Ground Week Four

07 June Brickwork Week Five

14 June Cementing the Floor Week Six

5 July Damp Proofing Week Nine

12 July Floor Screed Week Ten

19 July Work to grounds Week Eleven

26 July Pathways Week Twelve

02 August Carpentry Work Week Thirteen

09 August Windows Week Fourteen

16 August Wall Lining Week Fifteen

23 August Plastering Week Sixteen

30 August Carpenters Week Seventeen

6 September Carpenters Week Eighteen

13 September Electricians Week Nineteen

20 September Painters Week Twenty

27 September Finishing Touches Week Twenty-One

4 October The Opening Week Twenty-Two

 