Christ Church Undercroft Works
|
Week One 11th May 2004 |
|||||
|
On Tuesday 11 May our builders, Baker & Davies PLC, moved in to begin the enlargement and refurbishment of our undercroft rooms. A site office was set up in the room under the chapel, a builders compound was fenced off from the rest of the church grounds, while delivery was taken of materials and machinery. |
|||||
|
|
Pathfinders Room is converted into our builders site office. Materials begin to arrive. |
|
Our site manager spends a lot of time on the phone making arrangements and chasing deliveries. |
||
|
|
|
|
|
||
|
The first excavator arrives. |
|
The old choir vestry wood block floor and cupboard doors are removed. |
|
||
|
|
|||||